Let’s move on: As announced last year, we are building another classroom for the Rainbow School. This time in solid construction. The floor slab has already been poured. The aim is for the building to be completed in February 2024, after the school holidays. This will allow lessons to take place for 3 full school classes with around 70 children. We are currently looking for an additional teacher and have promised Rainbow School to cover the salary costs for one year. We are looking for “teacher sponsors” for the remaining years so that the children can receive high-quality lessons.
The building was erected within a few weeks: Construction began with the pouring of the foundations in September 2023 and the entire building was completed from mid-November to Christmas ’23. The interior of the classroom was completed by January 2024, and an ablution block was also finished.